Construction Schedule
Construction is anticipated to occur over a period of 2 months starting in late April 2026 and completed by the end of June 2026.
Work will take place 7 days a week. The work zone, with alternating traffic, will be present, even at nighttime. Through the construction period, the bridge will remain open.
| Item: | Timeline: |
| Anticipated Start Date for Construction | May 1 |
| Phase 1: NB to PEI | 21 Days |
| Phase 2: PEI to NB | 21 Days |
| Anticipated End Date for Construction | Late June |
*While every effort will be made to adhere to the schedule outlined above, timelines may be adjusted due to weather conditions, operational requirements, or other unforeseen circumstances.