Construction Schedule

Construction is anticipated to occur over a period of 2 months starting in late April 2026 and completed by the end of June 2026.

Work will take place 7 days a week. The work zone, with alternating traffic, will be present, even at nighttime. Through the construction period, the bridge will remain open.

 

Item:Timeline:
Anticipated Start Date for ConstructionMay 1
Phase 1: NB to PEI21 Days
Phase 2: PEI to NB21 Days
Anticipated End Date for ConstructionLate June

 

*While every effort will be made to adhere to the schedule outlined above, timelines may be adjusted due to weather conditions, operational requirements, or other unforeseen circumstances.